Bridge Street Reconstruction Project

CitySeal-CENTER


The Chapter 90 Bridge Street Reconstruction Project’s contract has been awarded to the general contractor Allied Paving. Construction activities are expected to begin within the next couple of weeks. Allied Paving has begun some preliminary work including construction markings, traffic barrels etc. Paper notifications have been handed out to all abutters in the work area, and message boards will be placed at the intersection of Hildreth St., and the intersection of VFW. Highway.

Phase 1 (VFW Highway to W.6th intersection) excavation will begin on the west side starting near West Third St. next week June 26, 2017.
Work will not be permitted to begin on the east side until the west side is completed.
The anticipated completion date for all of Phase 1 is August 15, 2017.

Phase 2 (W. 6th St to Willard St) will begin upon completion of Phase 1, with an anticipated completion around the end of November.

Work Included in both phases will include:
- Saw-cutting of the Roadway 1’ off of the curb.
- Tree Trimming
- Excavation of the existing sidewalks
- Removal and resetting of the granite curb
- Placement of new brick and concrete sidewalks
- Grinding and paving of the roadway
- Pavement markings
- Traffic detection cameras
- Planting of new street trees