Motion 05.06.08 Andover St.
|
|
OFFICE OF THE CITY MANAGER
CITY HALL
TELE: (978) 970-4000
FAX: (978) 970-4007
Bernard
F. Lynch
City
Manager
TO: Mayor Edward “Bud” Caulfield
And
Members
of the
FROM: Bernard F. Lynch, City Manager
DATE: June 6, 2008
SUBJECT: CC
Motion of 08.05.06 BY C.Kazanjian
“Request the Manager have the
department of public works provide the
In regards to the above-mentioned
motion, TJ McCarthy, Assistant Manager/DPW Operations has met with Lisa DeMeo,
City Engineer to evaluate the current sidewalk conditions and prepare a cost
estimate for repairing/installing sidewalks on both sides of
Below are the preliminary estimates for such project:
Excavate/remove existing sidewalk and replace with new 5’ wide sidewalk $420,000
Curb removal/reset at wheelchair ramps (only) $ 18,000
Adjust water gates/loam and seed $ 18,000
This estimate will
be included in the Department of Public Work’s Capital Plan in future updates
to the City of
Thank you.