TO: Mayor William F. Martin, Jr.
And
Members
of the Lowell
City Council
FROM: Bernard
F. Lynch, City Manager
DATE: November
26, 2007
SUBJECT: Billerica
Power Plant Project
___________________________________________________________________________
In response to previous requests,
I want to update the Council on the status of the Billerica power plant project. For the past
year the project has been making its way through the Massachusetts
Environmental Protection Act (MEPA) project review process. In January 2007,
Secretary of Environmental Affairs Ian Bowles ordered the preparation of an
Environmental Impact Report (EIR). A Draft Environmental Impact Report (DEIR)
was filed in September 2007. On November 1, 2007, Secretary Bowles issued a
Certificate on the DEIR in which he required the preparation of a Final EIR
(FEIR). Secretary Bowles ordered the applicant to provide additional
information on wetlands, stormwater, water supply, air quality, noise, hazardous
waste impacts, and mitigation.
The two most likely impacts to
residents of Lowell
pertain to air quality and noise. Secretary Bowles noted that the project
generally complies with State air quality criteria and that the Massachusetts
Department of Environmental Protection (DEP) did not cite any concerns in this
regard. As noted above, however, the FEIR will provide further information on
air quality. Likewise, the Secretary found that noise associated with the plant
will not exceed State or local limits.
We will continue to follow this
project and make sure Lowell
residents’ interests are protected. Please contact me if I can provide further
information in this regard. Thank you.