South Common Phase 2

Completed: November 2023
Address: 200 South Street
Neighborhood: Back Central
Project Cost: $698,500
Funding Source:

PARC + CDBG Grants

Project Scope: Irrigation added for the multi-purpose athletic field

Summer Street and South Street parking lot reconfigured to accommodate handicap parking

ADA-accessible paths installed between the parking lot and the track

Multilingual welcome signs installed at the Summer Street by South Street entrance

13 new trees planted
Landscape Architect: Huntress Sports
Contractor: Desmond Contracting 