South Common Phase 2

Completed: November 2023
Address: 200 South Street
Neighborhood: Back Central
Project Cost: $698,500
Funding Source:

PARC + CDBG Grants

Project Scope: Irrigation added for the multi-purpose athletic field

Summer Street and South Street parking lot reconfigured to accommodate handicap parking

ADA-accessible paths installed between the parking lot and the track

Multilingual welcome signs installed at the Summer Street by South Street entrance

13 new trees planted
Landscape Architect: Huntress Sports
Contractor: Desmond Contracting 
  1. 1 IMG_9233
  2. 2 IMG_6505-2
  3. 3 IMG_6488-2
  4. 4 IMG_6494-2
  5. 5 IMG_6502-2
  6. 6 IMG_6503-2
  7. 7 IMG_6196-2
  8. 8 IMG_6197-2

Project Documents:

South Common Master Plan

South Common Phase 2 100% Construction Documents