South Common Phase 3
Completed November 2024
| Address: | 200 South Street |
| Neighborhood: | Back Central |
| Project Budget: | $728,000 |
| Funding Source: | PARC + ARPA + CDBG |
| Project Scope: | Renovation of historic stage in amphitheater area Installation of demonstration rain garden with educational signage Installation of multilingual wayfinding signage on Thorndike Street across from train station Planting and tagging at least 35 trees as part of the South Common Arboretum |
Project Documents:
South Common Master Plan
6/1/2024 Final Construction Drawings
10/1/2023 Community Engagement Boards:
Construction Progress Photos:
-
6/11/2024