IFB 25-69: Reconstruction of Streets (COMPLETED)

2025 Reconstruction Street Map

Project Description: Reconstruction of roadway and sidewalk on the streets listed below.


Estimated Start Date: April 2025


Estimated Completion Date: December 2025


Estimated Cost: $6,831,080.90


Contractor: Newport Construction Corp.


City Contact: Engineering Office 

            Phone: 978-674-4070 

                        Email: Engineers@lowellma.gov

2025 Road Reconstruction Streets List

StreetFrom 
ToStart DateProgress
Ashland St  
Georgia Ave  
Sanders Ave  
April 2025Completed 
Barasford Ave  
Andover St 
East Merrimack St
June 2025Completed 
Broadway St
Walker St 
 Pawtucket St  
May 2025Completed 
Douglas Rd (Sidewalks)
Andover St
Gerson Terr.
July 2025Completed 
Douglas Rd (Paving) 
Frothingham St / Hovey St
Glenellyn Rd / Gerson Terr. 
April 2025Completed 
Grand St
Westford St 
Chelmsford St
April 2025Completed 
Leverett St 
Washington St
Cambridge St
April 2025Completed 
Magnolia St 
Varnum Ave
Pawtucket Blvd 
May 2025Completed 
Morey St
Light Ave 
 Pine St   
June 2025Completed 
Pembroke St  
Georgia Ave   
Sanders Ave  
April 2025
Completed 
Phebe Ave
Sarah Ave
Bodwell Ave
April 2025
Completed 
Ruth St 
Wedge St 
Parker St
April 2025
Completed 
Seventh Ave   
Mammoth Rd 
University Ave 
May 2025Completed 
Third St 
Bridge St 
Simpson St
September 2025 (Scheduled)Completed  
Washington St
Lincoln St
Hale St 
April 2025
Completed 
Windsor Park Rd 
Andover St 
East Merrimack St
July 2025Completed 

Notes: