IFB 25-85: Wheelchair Ramps and Sidewalk Repair - FY 2026

2026 Repair of Sidewalks and WCRs in the City of Lowell-Map

Project Description: Repair of existing sidewalk and wheelchair ramps in order to fix hazards and increase ADA compliance.



Estimated Start Date: August 2025


Estimated Completion Date: May 2028


Estimated Cost:

FY25: Bid Amount = $1.1 M - 100% complete

FY26: Bid Amount = $1.1 M - Underway

FY27: Bid Amount = $1,208,900.20


Contractor: Tasco


City Contact: Engineering Office 

            Phone: 978-674-4070 

                        Email: Engineers@lowellma.gov



2026 WCR AND SIDEWALK REPAIR LOCATIONS 

In 2026, the City will shift its focus to parks and residential neighborhoods outside of downtown that experience high pedestrian activity and have a documented history of accessibility requests. Several of these locations have also received MassDOT funding for Rectangular Rapid Flashing Beacons (RRFBs) to enhance pedestrian crossing safety.

LocationTotal WCRTotal Sidewalk RepairConstruction Status
Father Grillo Park4500 ftSpring 2026
Durkin Park16400 ftSpring 2026
Eagle Park12100 ftSpring 2026
Tyler Park21200 ftSpring 2026
Callery Park20200 ftSpring 2026
Lowell Housing Authority 20100 ftSpring 2026
Haddley Park1150 ftSpring 2026
Total1041,550 sf

2026 WCR AND SIDEWALK REPAIR LOCATIONS MAP

  1. 1 2026 Capital Project - Sidewalk Streets - City website-7 - St Antonys Church
  2. 2 2026 Capital Project - Sidewalk Streets - City website-1 - Durkin Park
  3. 3 2026 Capital Project - Sidewalk Streets - City website-2 - Eagle Park
  4. 4 2026 Capital Project - Sidewalk Streets - City website-3 - TYLER PARK
  5. 5 2026 Capital Project - Sidewalk Streets - City website-4 - Callery Park
  6. 6 2026 Capital Project - Sidewalk Streets - City website-5 -Lowell Housing Authority
  7. 7 T1455.03_Concept_Revised_01-22-25_DRAFT compressed_Page_1
  8. 8 2026 Capital Project - Sidewalk Streets - City website-6 -Hadley Park

2025 WCR AND SIDEWALK REPAIR LOCATIONS MAP